Harbor Lane Provisions - board minutes, 8 December 2025 - confidential | Page 2
4. FundingAmara Osei proposed paying for the budget with a seven-year term loan of $3.5 million from Port Ellery Savings Bank at a fixed 5.9 percent, and $2.17 million from cash, which stood at $4.8 million at the end of November. The loan keeps net debt below one and a half times earnings throughout.
5. Decisions
1.The board approved the North Pier budget of $5,670,000, contingency included.
2.The board approved the term loan of $3,500,000 and authorised the Managing Director and the Finance Director to sign it.
3.Spending beyond the contingency needs the board's approval in advance.
4.The North Pier distribution centre opens on 1 December 2026.
6. Actions
Order the racking and the dock doors
Choose the warehouse management system
Tell our largest customers about North Pier
Report on the budget at every board meeting
Next meeting: Monday 12 January 2026 at 9:00. The chair closed the meeting at 11:40.
Signed as a true record: Grace Holloway, chair